Written question WQ100309
- Asked by
- John ClarkReform
- To be answered by
- Cabinet Minister for Enterprise, Connectivity and Energy
- Tabled
- Due
- Answered
- Time to answer
- 9 days
Question
Will the Cabinet Minister confirm the dates on which the GG 119 Road Safety Audit for the A5 Menai suspension bridge approaches were commissioned and completed following the February 2026 vehicle collision, and the date on which the speed cushions were installed?
Answer
Answered by Deputy Minister for Transport (Mark Hooper)
The report was commissioned and completed on the 21st of April with installation taking place on the 4th of June 2026.